For a project where land is recovered by the State, will each locality the project passes through draw up its own policy framework and send it to the ministries and agencies that own the investment project, or must the ministries and agencies that own the investment project collect the data themselves and draw up the policy framework to submit to the Ministry of Natural Resources and Environment for appraisal before it goes to the Prime Minister?
Đào Chiến Thắng (HCMC)….
The Ministry of Natural Resources and Environment answers as follows:
Article 17 of Government Decree No. 47/2014/ND-CP dated May 15, 2014, on compensation, support and resettlement when the State recovers land, provides:
“Article 17. Compensation, support and resettlement when the State recovers land to implement investment projects whose investment policy is decided by the National Assembly or approved by the Prime Minister; land recovery projects involving multiple provinces and centrally run cities
Compensation, support and resettlement when the State recovers land to implement investment projects whose investment policy is decided by the National Assembly or approved by the Prime Minister, and which require relocating an entire residential community and affect the community's whole life, socio-economic situation and cultural traditions, as well as land recovery projects involving multiple provinces and centrally run cities, are carried out as follows:
1. The ministry or sector that owns the investment project is responsible for leading, in coordination with the provincial People's Committee of the place where land is recovered, the drawing up of a compensation, support and resettlement policy framework to submit to the Prime Minister for consideration and decision, and must ensure funding for compensation, support and resettlement as prescribed.
The compensation, support and resettlement policy framework includes the following main contents:
a) The area of each type of land expected to be recovered;
b) The number of organizations, households and individuals using land in the area expected to be recovered;
c) The expected level of compensation and support for each category of person whose land is recovered; the expected compensation land price for each type of land and each location category;
d) The resettlement arrangement plan (expected number of resettled households, locations and forms of resettlement);
đ) The expected total amount of compensation, support and resettlement and the source of funds to carry it out;
e) The expected schedule for implementing the compensation, support and resettlement plan;
g) The expected time and plan for relocation and handover of the site.
The compensation, support and resettlement policy framework must set out the above contents for the whole project and in detail down to each locality (if applicable). Where land is recovered to implement an investment project that requires building a concentrated resettlement area, the contents prescribed in this clause must also cover the area of land recovered to build that concentrated resettlement area.
2. The Ministry of Natural Resources and Environment leads, in coordination with relevant agencies and organizations, the appraisal of the compensation, support and resettlement policy framework before it is submitted to the Prime Minister for decision.
3. Based on the compensation, support and resettlement policy framework decided by the Prime Minister, the provincial People's Committee organizes the drawing up, appraisal and approval of the compensation, support and resettlement plan for the project in the locality, after obtaining written approval from the ministry or sector that owns the investment project; it organizes implementation and settles the compensation, support and resettlement funds with the ministry or sector that owns the investment project.”
Compiled